How concrete polishing worksFrom grind to shine.

Polishing concrete is a sequence of diamond passes, each finer than the last. Skip one and it shows in the light. Here's what happens to your slab.

How concrete polishing works: a Grind to Shine job

Eight
passes

Grit is the size of the diamonds. Low numbers cut, high numbers polish.

  1. 30

    Open

    Metal-bond diamonds cut through the top skin and open the slab to your exposure.

  2. 60

    Flatten

    Takes out the scratches from the first cut and levels high spots.

  3. 120

    Refine

    Last metal pass. Holes and cracks get grouted to match.

  4. 200

    Densify

    A liquid hardener soaks in and makes the surface tougher.

  5. 400

    Hone

    Resin pads start to bring up a matte sheen.

  6. 800

    Polish

    A soft satin glow. Many floors stop here.

  7. 1500

    Polish

    The reflection sharpens up.

  8. 3000

    Shine

    Mirror finish, then a penetrating guard against stains.

On a
new build

The best floors happen in two visits, planned around your builder.

  1. 1Week 0

    Slab poured

    Give it about four weeks to cure before we grind. Tell your builder early that the floor is getting polished, so they protect the slab.

  2. 2Lock-up

    First grind

    Once the frame's up and the roof's on, we grind to your exposure. No walls in the way means right to the edges.

  3. 3Trades

    Plasterers & fit-out

    The floor gets covered while everyone else works. Small knocks come out in the final polish.

  4. 4Pre-handover

    Final polish & guard

    We hone up to your sheen, harden the surface and seal it. This is where the shine comes up.

  5. 5Handover

    Move in

    No curing time and nothing to peel. Mop it with a pH-neutral cleaner and it'll look like this for years.