How concrete polishing worksFrom grind to shine.
Polishing concrete is a sequence of diamond passes, each finer than the last. Skip one and it shows in the light. Here's what happens to your slab.

Eight
passes
Grit is the size of the diamonds. Low numbers cut, high numbers polish.
- 30
Open
Metal-bond diamonds cut through the top skin and open the slab to your exposure.
- 60
Flatten
Takes out the scratches from the first cut and levels high spots.
- 120
Refine
Last metal pass. Holes and cracks get grouted to match.
- 200
Densify
A liquid hardener soaks in and makes the surface tougher.
- 400
Hone
Resin pads start to bring up a matte sheen.
- 800
Polish
A soft satin glow. Many floors stop here.
- 1500
Polish
The reflection sharpens up.
- 3000
Shine
Mirror finish, then a penetrating guard against stains.
On a
new build
The best floors happen in two visits, planned around your builder.
- 1Week 0
Slab poured
Give it about four weeks to cure before we grind. Tell your builder early that the floor is getting polished, so they protect the slab.
- 2Lock-up
First grind
Once the frame's up and the roof's on, we grind to your exposure. No walls in the way means right to the edges.

- 3Trades
Plasterers & fit-out
The floor gets covered while everyone else works. Small knocks come out in the final polish.

- 4Pre-handover
Final polish & guard
We hone up to your sheen, harden the surface and seal it. This is where the shine comes up.

- 5Handover
Move in
No curing time and nothing to peel. Mop it with a pH-neutral cleaner and it'll look like this for years.